上橫高速一期工程第一合同段伸縮縫施工圓滿完成
10月24日(ri),隨著公義2#橋最后(hou)一段伸縮縫安裝到(dao)位,標(biao)志著上橫高(gao)速一期(qi)工程(cheng)第一合同段伸縮縫施(shi)工圓滿完(wan)成,為(wei)實現(xian)年底通車目(mu)標(biao)夯實基礎。
上橫(heng)(heng)高速(su)一(yi)期(qi)工(gong)程第一(yi)合同段全長19.83公里,雙向四車道(dao),設計(ji)時(shi)速(su)120km/h,標段內主線、互通橋(qiao)梁20座,伸縮(suo)縫(feng)(feng)共計(ji)76道(dao)。為確保橋(qiao)梁伸縮(suo)縫(feng)(feng)施(shi)(shi)工(gong)順利進行(xing),上橫(heng)(heng)高速(su)公司實(shi)施(shi)(shi)標準(zhun)化(hua)(hua)、規范化(hua)(hua)、精細化(hua)(hua)的過程管控(kong),克(ke)服工(gong)期(qi)緊、任務(wu)(wu)重、交叉施(shi)(shi)工(gong)等多重困(kun)難(nan),因地制(zhi)宜優(you)化(hua)(hua)方案和施(shi)(shi)工(gong)工(gong)序(xu),嚴格落實(shi)標準(zhun)化(hua)(hua)施(shi)(shi)工(gong)管理(li)。項目成(cheng)立伸縮(suo)縫(feng)(feng)管理(li)專班,多次組織召開(kai)施(shi)(shi)工(gong)現場部(bu)署會(hui),在每(mei)道(dao)伸縮(suo)縫(feng)(feng)澆筑完(wan)成(cheng)后及時(shi)總結經驗,確保伸縮(suo)縫(feng)(feng)施(shi)(shi)工(gong)優(you)質、高效、有序(xu)推進,按計(ji)劃圓滿完(wan)成(cheng)了(le)全部(bu)的伸縮(suo)縫(feng)(feng)施(shi)(shi)工(gong)任務(wu)(wu),為全面(mian)完(wan)成(cheng)標線施(shi)(shi)工(gong)提供了(le)作業面(mian)。
上橫高(gao)速建成(cheng)后,將逐步完善廣西北部(bu)灣經(jing)濟(ji)區(qu)路(lu)網結(jie)構(gou),全力助(zhu)推自治區(qu)“五(wu)網”重(zhong)大基礎(chu)設(she)施建設(she),增強南寧市(shi)核(he)心經(jing)濟(ji)區(qu)的(de)(de)輻(fu)射能力,對(dui)進(jin)一步改善上林縣、賓陽(yang)縣、橫州市(shi)的(de)(de)基礎(chu)設(she)施建設(she),拉動沿線(xian)經(jing)濟(ji)及旅(lv)游(you)業快速發展,全面(mian)推進(jin)鄉(xiang)村振興具有重(zhong)要作用。